As an excellent supplier of prefabricated integrated housing, Honglianzhong has successively undertook the construction of temporary prefabricated housing projects with a total area of more than 50,000 square meters around the main venue of the National Olympic Sports Park and the “Bird’s Nest” of the National Stadium. Provided strong support and won the honorary certificate issued by the 29th Olympic Organizing Committee. In March 2009, Honglianzhong successfully undertook the construction of more than 30,000 square meters of color steel prefabricated houses in the “60th Anniversary of the Founding of the People’s Republic of China, the National Day Military Parade Village”. In recent years, Honglianzhong has also provided services for the project department of China Airport Capital New Airport, the construction project of the new CCTV station, the National Grand Theater project, Beijing Metro Line 4, Tianjin Metro, Tianjin Airbus 320 assembly workshop project, and the comprehensive improvement of Tianjin city appearance and environment. Project departments such as the General Headquarters and the Parade Village of the 15th Army of the Chinese People’s Liberation Army (Hubei Province) have designed and installed a variety of standard and luxurious prefabricated houses, which have won unanimous praise from customers for their excellent product quality and good corporate reputation.

 After the “5.12” Sichuan earthquake in 2008, Beijing Honglianzhong and Hubei Honglianzhong actively participated in the upsurge of aiding and building transitional resettlement houses in the disaster area. In less than two months, they successfully completed the production of more than 200,000 square meters The task of aiding the construction of prefabricated houses has handed over a perfect answer to the people in the disaster-stricken areas of Sichuan! Participated in the construction of “Vulcan Mountain Hospital” on January 24, 2020, and completed the construction on February 2, 2020. Honglianzhong Group and the people of the whole country have made our due efforts to win the epidemic prevention and control battle without gunpowder smoke contribute! In order to maintain sustainable and stable development, the company has further increased the intensity of structural adjustment. Honglianzhong is based in Beijing as the leading market, and expands Tianjin, Tanggu, Harbin, Hohhot, Xi’an, Chengdu, Shijiazhuang, Wuhan, Changsha, and Urumqi as the second market. Respond to market demand in the first time and better serve our customers.

I. Wuhan Caidian Huoshenshan Hospital Project

Project address: Caidian District, Wuhan

Total construction period: January 24, 2020- February 2, 2021

Project overview: Huoshenshan Hospital in Caidian, Wuhan, is to focus on the treatment of patients with novel coronavirus pneumonia by referring to the model of Xiaotangshan Hospital during the fight against SARS in 2003. The total construction area of the hospital is 33900 square meters, with 1000 beds arranged. It has established intensive care units, intensive care units, and general wards, as well as auxiliary departments such as infection control, testing, special diagnosis, and radiation diagnosis. There are no outpatient clinics. It only takes 10 days from scheme design to construction transaction payment, known as China’s speed. Our company actively responded and immediately launched the establishment of the leading group of Honglianzhong Group’s “epidemic prevention” emergency plan. Mr. Wang Yuzhang, the president of the group, served as the commander in chief, and established the pioneer “epidemic” group of Honglianzhong Group’s “Xiaotangshan Hospital” in Wuhan Huoshen Mountain to rush to the forefront of epidemic disaster relief at the first time. A total of approximately 300 sets of box rooms will be used.

II. Xinjiang Epidemic Project

Project address: Changchun Road, Ürümqi

Total construction period: July 25th, 2020 to August 31st, 2020

Project overview: The project is the 2020 Xinjiang Epidemic Project, which is located in Tianshan District and the new urban area of Urumqi. Among them, there are 300 standard box rooms and 100 walkway boxes in Tianshan District, Urumqi; There are 113 standard box rooms, 283 aisle boxes, 5 functional boxes, 6 staircase boxes, 2 kitchen operation rooms, and 142.37 square meters of glass curtain walls in the new urban area of Urumqi.

III. Xiong’an Project

Project address: Rongdong and Rongxi areas of Xiong’an, Hebei

Total construction period: May 2020 to April 2021

Project overview: This project is the 2020 Xiong’an project. Beijing Honglianzhong Light Steel Structure Housing Co., Ltd. undertook to build the Xiong’an project on May 23, 2020, with a total construction area of 36890㎡. It took more than 10 months from mobilization to demobilization to supply more than 2000 box houses for Xiong’an Project and complete installation; The project of Xiong’an will construct 2 concave shaped buildings, 3 Hui shaped buildings and 21 H shaped buildings in total.

IV. Apartment Building Project of Beijing Honglianzhong Group

The construction area of the passive apartment building project is 3057㎡, with one basement floor and three floors above the ground, of which the three floors above ground are constructed according to the standard of the German Passive House Institute Group Co., Ltd. (PHI) designs, processes and constructs. The certification application was filed in October 2018, the certification contract was signed in July 2019, the airtightness inspection was passed in January 2021, and the certification achieved in July 2021. It is the world’s first multi-layer thin-walled light steel that has passed PHI certification Passive house apartment project.

V. Project Case of Beijing Honglianzhong Group

The passive house of Beijing Honglianzhong Group has a shear wall structure underground and a thin-walled light steel structure on the ground. There are viewing platforms locally and windows around. The cornice height is 10.85 meters, which increases the heat preservation, Difficulty in design and construction in terms of air tightness, doors and windows, and fresh air.

VI. Passive House Office Building Project of Beijing Honglianzhong Group

The construction area of the passive R&D building project is 4347.87㎡, with one basement floor and five floors above the ground, of which the five floors above ground are constructed according to the standard of the German Passive House Institute (PHI). ) Co., Ltd. designed, processed and constructed.

VII. Cold-Formed Thin-walled Light Steel Structure

Cold-formed thin-walled light-steel residences first evolved from wooden structures, mainly in some developed countries, such as the United States, Canada, Australia and Europe. After a century of development, application and practice accumulation, low-rise residential buildings in the above countries have formed The main composition forms, and have formed a unique design and construction specifications. After more than a hundred years of development, a mature construction system with excellent physical properties, flexible space and shape, easy construction and various forms has been formed.

VII. Light Steel Villa

The cross-sectional area of light steel keel structure building components is the smallest among all building types. Under the premise of meeting the same bearing capacity, the weight is the lightest, and light functional building materials are used. The overall weight is about 1/5- 1/6; the building foundation requirements are lower than traditional buildings, and the project cost is reduced accordingly.

The thickness of the enclosure wall of the light steel keel structure building is 14-20cm, and the building usable area is 10% larger than that of the concrete structure building.